![]()
|
|||||||
|
©
2001 |
Residents
seek solution to sewer quandary
Residents of the Buck Run III
subdivision in Sisters are trying to find a way to hook up to the city sewer
system without breaking the bank.
A group of property owners
met with Sisters city councilors on Thursday, November 1, with a proposal
to pay for the installation of sewer main lines but wait for 10 years
to hook up to the system.
Buck Run III was never included
in the original plans for the sewer system, but the residents are required
by law to hook up once the system is available. Most of the property owners
were unaware that that meant they would have to pay to put their own main
lines and laterals in neighborhood streets.
Many property owners have
already spent thousands of dollars on septic systems that will have to
be abandoned when they hook up to the sewer system.
Attorney Robert Lovelein,
who spoke for four of the 13 property owners affected, said they would
be willing to form a Limited Improvement District (LID) or some other
organization to fund at least a portion of main line construction at a
rate of about $4,000 per lot.
The property owners also want
the city to give them a 10 year grace period before being required to
hook up -- unless their septic systems fail. That way, the residents would
get full use from their expensive septic systems before having to pay
Systems Development Charges and install laterals to their homes to hook
up to the sewer.
City councilors agreed to
continue exploring a solution along these lines -- but there are hurdles.
The first is cost. The city
engineer, Dick Nored, estimates mainline construction in the Buck Run
III neighborhood at between $90,000 and $100,000. The property owners
had been operating on an early rough city estimate of $65,000.
The residents are offering
to pay some $48,000, with another $10,000 to come from developers of nearby
Coyote Springs and with the city to make up the difference.
It is possible that a private
group could get the work done more cheaply than the city because they
would not face government requirements to pay "prevailing wage." According
to city public works director Gary Frazee, "prevailing wage" can be as
much as two times market wages.
But at least one councilor
has his doubts.
"I think $48,000 won't get
the lines in," said Councilor Lon Kellstrom. "$48,000 won't even get close,
in my opinion, even if you do it privately."
Another question is whether
the Department of Environmental Quality will allow residents to wait 10
years to hook up to the system. The agency could revoke residents' septic
permits, according to city attorney Steve Bryant.
The city has no control over
DEQ's permitting process, Bryant noted.
"It's something to be aware
of and know that that's at least a little bit of a risk," the attorney
said.
Lovelein said that property
owners really aren't prepared to pay more than about $400 per year to
finance the project. And, he noted, he only speaks for some of those affected.
The whole group would need to decide if a financing plan is the way they
want to go.
The city council will meet
with the property owners again on November 15, to refine cost estimates
and discuss engineering possibilities.
|
|
|||||