![]()
|
||||||||
|
The on-line Nugget does not feature all the stories of our print edition. For all the news, subscribe here. ©
2002 |
District
accepts new bids on school Work will go
forward on the next phase of construction for the new Sisters High School
-- but not without considerable wrangling over the bids.
Only one contractor -- Kirby
Nagelhout Construction -- bid on four of the five elements of the second
bid package. Nagelhout is also the project's Construction Manager/General
Contractor.
Doug Miller Construction landed
the contract for site utilities for $330,000 plus bond costs. Miller's
bid was just over half the bid placed by Nagelhout.
But on concrete, carpentry,
and structural steel work, Nagelhout was the only bidder, which displeased
the school board.
The board discussed the bidding
process at length in a special meeting on Wednesday, June 12, questioning
whether there had been enough time allowed for competitors to put together
bids.
Time did appear to be a factor.
Construction project manager Bob Martin reported that at least a couple
of contractors "would have liked to put together a bid but they found
out too late."
Board members expressed concern
that the construction team cut the time frame for information too close,
although it appears that plans were made available in most plan centers
in the state in a timely fashion.
The board debated whether
to reject Nagelhout's bid and put elements of Bid Package #2 out on the
street again.
A delay, especially in doing
concrete work, could have set the whole project back by a month, and the
board could not countenance that delay.
"It's too late because of
the impact to the schedule to do anything about anything but the steel,"
said board member Steve Keeton.
The board agreed to accept
Nagelhout's bid of $1,210,934 on structural steel. However, the board
insisted that Nagelhout in turn bid out steel fabrication and erection
separately, with bids going to school district offices.
The board also accepted the
sole bid of $944,096 on concrete and a $116,259 rough carpentry bid and
a $40,571 finish carpentry bid.
All bids are under budget.
The board also emphasized
to Nagelhout and Steele Associates Architects that they are to do everything
possible to ensure a range of competitive bids on all future phases of
the project.
Mass excavation has been completed
on the $21 million Sisters High School project.
The district hopes to open
the new school in September 2003. |
|
||||||