![]()
|
||||||||||
|
The on-line Nugget does not feature all the stories of our print edition. For all the news, subscribe here. ©
2002 |
School
requires massive dig
An error in aerial
mapping of the new Sisters High School site has left excavators short of
the dirt they need to lay the groundwork for the facility.
To make up the shortage, excavators
have dug a massive 20-foot deep "borrow pit" and extracted some 35,000
cubic yards of dirt.
The engineering firm of Hickman,
Williams & Associates has taken responsibility for the mistake, laying
the error at the feet of their mapping subcontractor 3Di of Eugene.
"It is apparent that the contours
on the mapping are not accurate -- on the order of half-a-foot to one
foot," said Matt Steele of Hickman, Williams at a school board meeting
on Monday, June 24.
"We're hoping that (3Di) will
stand up to the plate, but if they don't, we'll take the hit," Steele
said.
The financial impact of the
error is estimated at about $70,000.
Because the borrow pit 360-foot-by-160-foot
was dug on the site of future playing fields, it will have to be filled
in. The school board is looking for ways to get some benefit out of the
need to fill the pit.
The board is considering expansion
of a planned pond at the west end of the site that was to be used for
natural resources education.
Board member Steve Keeton
thinks that the pond could be used as an irrigation reservoir, saving
the district considerable money both in pumping equipment and in long-term
operating costs.
The board is also looking
into digging out an amphitheater that could later be used for school and
community events and activities.
The board agreed that none
of these options should create an added expense to the district. |
|
||||||||