![]()
|
|||||||||
|
The on-line Nugget does not feature all the stories of our print edition. For all the news, subscribe here.
©
2002 Display
Advertising The
contents of the on-line edition of The Nugget represent a selection
among the stories that appear in the weekly print edition. |
New
high school may open early A snow-free and
sunny fall may be bad news to skiers, but it has been a boon to the construction
crews building the new Sisters High School.
"Because we've been blessed
with such good weather, we're moving along nicely," said School District
Construction Manager Bob Martin at the Monday, December 2, school board
meeting.
In fact, the project is moving
along well ahead of schedule.
According to Superintendent
Steve Swisher, "certain portions are significantly ahead -- perhaps as
much as five weeks."
The quick pace may mean the
school can be opened earlier than the projected January 2004 target --
maybe even as early as September. The school board will make that call
in February, as they begin crafting next year's schedule.
According to Martin, it should
be clear by then whether the accelerated pace of building is holding up.
Current cost projections peg
the entire high school project at just shy of $21.6 million. That's almost
$600,000 over the $21 million budget, but the overage is still covered
within $1.17 million in contingency funds.
Project contractor Kirby Nagelhout
Construction Company (KNCC) is carrying $544,994 in contingency funds.
The Sisters School District
built up $969,733 in contingency funds through cost savings on the project.
The district has spent $345,010 of that amount to cover unanticipated
change-orders such as construction of additional water lines and to add
elements back into the project that had been relegated to an options list.
The $624,723 remaining has
been largely consumed by expenses that must be paid by the district outside
of the construction contract, such as sewer service, legal expenses, permit
fees and some engineering costs.
The "owner costs" are $571,268.02
over budget, including $200,000 the board has estimated for the purchase
of irrigation water rights.
The net result is that --
by using up savings -- the project costs are covered, but without much
room to spare.
Swisher and school board member
Eric Dolson continued to debate operational costs for the new school.
Swisher is projecting approximately $102,000, a figure Dolson believes
is optimistic.
Dolson believes the budgeting
for maintenance and custodial personnel is thin and he questions the calculation
of sewer fees. He also believes charges for city irrigation water should
be factored in in case the school district doesn't acquire water rights
and set up a system by next spring.
"You've made some very, very,
very optimistic assumptions here that concern me a lot," Dolson told Swisher.
Swisher adamantly defended
his figures.
"This is a good best estimate
for my part," he said. |
|
|||||||